Solving Complexity with precision

Can a Variation Be Initiated After the Taking-Over Certificate under FIDIC 1999?

home / Blog

Can a Variation Be Initiated After the Taking-Over Certificate under FIDIC 1999?

Variation after Taking-Over Certificate is a question that often arises in contract administration:

Can the Engineer initiate a Variation after the Taking-Over Certificate has been issued?

To consider this properly, we first need to understand what Taking-Over actually means and distinguish between a Variation and work required to remedy defects or complete outstanding work.

Sub-Clause 13.1 [Right to Vary] is the natural starting point.

It provides that Variations may be initiated by the Engineer prior to issuing the Taking-Over Certificate for the Works, either by an instruction or by requesting the Contractor to submit a proposal.

The reference to the Taking-Over Certificate is important.

Why does Sub-Clause 13.1 place the initiation of Variations before the Taking-Over Certificate?

For that, we need to look beyond Clause 13.

What happens when the Works are taken over?

Under Sub-Clause 10.1 [Taking Over of the Works and Sections], the Employer takes over the Works when the Taking-Over Certificate is issued in accordance with the Contract.

This should also be read together with Sub-Clause 17.2 [Contractor’s Care of the Works].

The Contractor is responsible for the care of the Works until the Taking-Over Certificate is issued. Once the Taking-Over Certificate for the Works is issued, responsibility for the care of the Works passes to the Employer, subject to the provisions of the Contract.

Now, if we go back to Sub-Clause 13.1, the reference to Taking-Over starts to make more sense.

Before Taking-Over, the Contractor is executing the Works and remains responsible for their care. Clause 13 provides the contractual mechanism through which Variations to the Works may be initiated.

After Taking-Over, the position is different. The Employer has taken over the Works and responsibility for their care has passed in accordance with Sub-Clause 17.2.

Against this background, the wording of Sub-Clause 13.1 becomes particularly relevant — the Engineer’s right to initiate Variations applies prior to issuing the Taking-Over Certificate for the Works.

But does this mean that the Contractor cannot be instructed to carry out any work after Taking-Over?

No. And this is where an important distinction needs to be made.

Variation or remedying defects?

Taking-Over does not mean that all of the Contractor’s obligations have come to an end.

There may still be outstanding work to complete. Defects may become apparent and require rectification. The Contractor may therefore be required to carry out work after the Taking-Over Certificate has been issued.

This takes us to Sub-Clause 11.1 [Completion of Outstanding Work and Remedying Defects].

Consider a practical situation.

After Taking-Over, part of an installed drainage system is found not to comply with the requirements of the Contract. The Engineer requires the Contractor to rectify it.

The Contractor is carrying out physical work after Taking-Over, and there may be an instruction requiring that work to be carried out.

But has the contractual requirement changed?

No.

The Contractor is being required to provide what the Contract already required. The fact that the work is carried out after Taking-Over does not, by itself, make it a Variation.

Now consider a different situation.

The drainage system has been completed in accordance with the Contract and the Works have been taken over. Subsequently, a different drainage arrangement is required which changes what was originally required under the Contract.

That is a different contractual situation.

The issue is no longer simply about completing outstanding work or bringing the Works into compliance with an existing contractual obligation. There is now a change to the contractual requirement itself.

This is why, when an instruction is issued after Taking-Over, the first question should not simply be:

“Has the Engineer issued an instruction?”

The better question is:

“Why is this work being instructed?”

Is the Contractor being required to complete outstanding work or remedy a defect in accordance with its existing contractual obligations?

Or is a new change being introduced to what the Contract originally required?

Once this distinction is understood, the relevant contractual provisions become much clearer.

What if the Variation process started before Taking-Over?

There is another situation worth considering.

Suppose the Engineer requested the Contractor to submit a proposal for a Variation before the Taking-Over Certificate was issued.

The Contractor submitted its proposal, but the proposal was still under review when the Taking-Over Certificate was subsequently issued.

What happens then?

This is different from attempting to initiate a completely new Variation after Taking-Over.

Sub-Clause 13.1 allows the Engineer to initiate a Variation before Taking-Over in two ways — by issuing an instruction or by requesting the Contractor to submit a proposal.

Therefore, if the Engineer requested the proposal before the Taking-Over Certificate was issued, the Variation process had already been initiated within the period contemplated by Sub-Clause 13.1.

The subsequent steps would then need to be considered in accordance with Sub-Clause 13.3 [Variation Procedure] and the particular circumstances of the Variation.

There is therefore an important distinction between:

Initiating a new Variation after Taking-Over, and continuing a Variation process which was initiated before Taking-Over.

They should not be treated as the same situation.

Connecting the provisions

So, can the Engineer initiate a Variation after the Taking-Over Certificate has been issued?

The answer becomes clearer when the relevant provisions are read together.

  • Sub-Clause 13.1 places the Engineer’s right to initiate Variations prior to issuing the Taking-Over Certificate for the Works.
  • Sub-Clause 10.1 deals with the Employer taking over the Works.
  • Sub-Clause 17.2 deals with responsibility for the care of the Works before and after Taking-Over, and
  • Sub-Clause 11.1 explains why the Contractor may still be required to carry out work after Taking-Over without that work necessarily being a Variation.

Therefore, when work is instructed after Taking-Over, the date of the instruction alone may not provide the complete answer.

We need to ask:

What is the contractual reason for the work?

Is the Contractor completing or remedying something already required under the Contract?

Or is there a new change to the contractual requirement?

And, if it is a Variation, when was the Variation process actually initiated?

These questions bring the relevant provisions together and help distinguish between work arising from the Contractor’s continuing contractual obligations and a new change to the Works.

That is often where the real value of understanding the contract lies — not simply knowing an individual Sub-Clause, but understanding how the provisions connect and operate together.


Relevant FIDIC 1999 Provisions

  • Sub-Clause 10.1 — Taking Over of the Works and Sections
  • Sub-Clause 11.1 — Completion of Outstanding Work and Remedying Defects
  • Sub-Clause 13.1 — Right to Vary
  • Sub-Clause 13.3 — Variation Procedure
  • Sub-Clause 17.2 — Contractor’s Care of the Works